Cost and schedule
reporting are done on a quarterly basis. The sub-project gets off the
right foot and after three months Bob reports the following summary:
%
planned (hrs) = 23.8
% complete (hrs) = 21.4
Delta = 2.4%
% spent (hrs)
=
23.3
The
project seems right on track in cost and a little bit behind schedule.
Since staying on schedule was one of the main objectives, the PM asks
Bob to look into this and take some corrective action |